Art. 77 2. Termine fissato in altro modo

1 Ove l’adempimento d’una obbligazione o d’altro atto giuridico debba aver luogo trascorso un dato termine dalla conclusione del contratto, esso dovrà effettuarsi:

1.
l’ultimo giorno del termine, se questo è fissato a giorni, non comprendendo nel computo del termine il giorno in cui fu conchiuso il contratto, e, se il termine è di otto o 15 giorni, s’intenderanno non una o due settimane ma otto o 15 giorni interi;
2.
quel giorno dell’ultima settimana che pel nome corrisponde a quello in cui fu conchiuso il contratto, se il termine fu stabilito a settimane;
3.
quel giorno dell’ultimo mese che per il numero corrisponde a quello in cui fu conchiuso il contratto, se il termine fu stabilito a mesi o ad uno spazio di tempo comprendente più mesi (un anno, un semestre, un trimestre), e, se un tal giorno manca nell’ultimo mese, l’adempimento avrà luogo l’ultimo giorno di detto mese.

L’espressione «mezzo mese» equivale al termine di 15 giorni, i quali si contano per gli ultimi, se il termine è di uno o più mesi e mezzo.

2 In egual modo è computato il termine anche se lo stesso abbia a decorrere non dal giorno del contratto, ma da altra epoca.

3 Ove l’adempimento debba seguire entro un certo termine, dovrà aver luogo prima dello spirare del medesimo.

Art. 77 2. Other time limits

1 Where an obligation must be discharged or some other transaction accomplished within a certain time limit subsequent to conclusion of the contract, the time limit is defined as follows:

1.
where the time limit is expressed as a number of days, performance falls due on the last thereof, not including the date on which the contract was concluded, and where the number stipulated is eight or fifteen days, this means not one or two weeks but a full eight or fifteen days;
2.
where the time limit is expressed as a number of weeks, performance falls due in the last week of the period on the same day of the week as the one on which the contract was concluded;
3.
where the time limit is expressed as a number of months or as a period comprising several months (a year, half-year or quarter), performance falls due in the last month of the period on the same day of the month as the one on which the contract was concluded or, where the last month of the period contains no such day, on the last day of that month.

The term ‘half-month’ has the same meaning as a time limit of fifteen days; if the time limit is expressed as a period of one or more months plus one half-month, the fifteen days are counted last.

2 Time limits are calculated in the same manner when stipulated as running from a date other than the date on which the contract was concluded.

3 Where an obligation must be discharged before a specified time limit, performance must occur before that time expires.

 