Art. 375 I. Withdrawal because estimate exceeded

1 Where an estimate agreed with the contractor is exceeded by a disproportionate amount through no fault of the customer, he has the right to withdraw from the contract before or after completion.

2 In the case of construction work carried out on his land or property, the customer is entitled to an appropriate reduction in the price or, if the work is not yet complete, to call a halt to the work and withdraw from the contract against equitable compensation for work already done.

Art. 374 b. D’après la valeur du travail

Si le prix n’a pas été fixé d’avance, ou s’il ne l’a été qu’approximativement, il doit être déterminé d’après la valeur du travail et les dépenses de l’entrepreneur.

 